Showing posts with label plumbing. Show all posts
Showing posts with label plumbing. Show all posts

Sunday, July 14, 2013

Bathroom Boogaloo: Days 6 & 7

On Day 6, the waste plumbing was completed and the space was framed out.  The new, rerouted supply lines were partially in place too.  On Day 7, after most of a day with the water turned off, the supply lines were in place and hooked up.  It was really nice to see the first indications of our future room taking shape.

Outside the new bathroom.

Inside the new bathroom, looking towards where the washer and dryer will go.


New water supply lines routed outside the space.

New connecting to old.

New washer hookups.

Now we wait for the plumbing inspection, coming up in a couple of days.




Thursday, July 11, 2013

Bathroom Boogaloo, Day 5

Yesterday, Day 5, I was out of the house.  I came home to find more refined waste plumbing.  Drains for the sink and washer had been added.  The big pile of dirt had been moved too.

Overview
Big pile of dirt, now more neatly piled.

Detail of waste plumbing.  The line shooting up to the upper right corner of the picture is for the sink.  In the lower left, capped in blue, is the shower drain. The toilet is in the middle.

Waste line for washer.



Tuesday, July 9, 2013

Bathroom Boogaloo, Days 3 & 4

Yesterday, Day 3, sounded pretty easy-going in comparison with Day 2's jackhammering.  From what I could tell, the hole was refined, waterproofing paint (Drylock) was applied to the brick, and the back wall of the room was framed up.


Future plumbing parts...these look exciting!

Day 4 saw (heard?) a lot more action.  Lots of power saw noises, and various times at which I could not use the water.  The result is fancy new bathroom guts!

The small line in bath is the new shower drain; the larger one in front is for the new toilet.